Federal Government Building Projects

Canadian Parliament - Centre Block (Heritage)

 X-L-Air was responsible for sprinklers, plumbing, HVAC and DDC controls

This work was done in two projects. The new Senate Committee Room was serviced with an air conditioning system consisting of two new air handling units (AHU's) which were installed in the basement. X-L-Air was responsible for sprinklers, plumbing, HVAC and DDC controls.

The South Face Pressurization project consisted of two 100% outside air conditioning units used to pressurize the corridor on the south face of the building, all floors allowing important stone preservation work to be done on the outside walls.

The old heritage solid wood doors were removed and equally solid vented temporary doors were installed in their place, to be replaced by the original doors when all restoration work was completed.

Working in Canada's most significant, high profile, heritage building added to the challenge X-L-Air met.

Justice Building, Wellington St. (Heritage)

The work involved new ducting and VAV systems, refurbishing of all HVAC and plumbing systems and new DDC controls.

X-L-Air was the prime mechanical contractor. This entire building was gutted and refurbished. As it is a heritage building and forms part of the Parliament Hill complex of buildings, special care had to be taken while doing the demolition and new installation work.

General Contractor: Axor
Project Manager: Public Works Government Services Canada (P.W.G.S.C.)

St. Andrews Tower - Department of Justice

XLAir responsible for mechanical systems including plumbing, heating, air conditioning

Major refit of 11 storey Federal Government Building. X-L-Air was responsible for all HVAC, sprinkler, DDC Controls and Plumbing Systems.

General Contractor: Thomas Fuller Construction (1958) Limited
Project Manager: PCL Construction Eastern Inc.
Owner: P.W.G.S.C.

Statistics Canada Main Building - Tunney's Pasture

X-L-Air was the general contractor

X-L-Air was the general contractor. Ducting, Variable Air Volume (VAV) boxes, ceilings, lighting and controls were demolished and replaced with new systems while the building was occupied.

General Contractor: X-L-Air Energy Services Ltd.
Engineer: Smith & Anderson

Revenue Canada - 875 Heron Road

XLAir responsible heating refit

X-L-Air was the general contractor. The entire high pressure to medium temperature heating water system of this large complex (three buildings), was gutted and replaced within six months. The schedule was strictly driven by the need to provide heating to two thousand public servants by the start of the heating season. New pumps, steam-to-water heat exchangers, controls and all electrics and motor control centres were replaced.

General Contractor & Project Manager: X-L-Air Energy Services Ltd.
Engineer: P.W.G.S.C.
Client: P.W.G.S.C.

Department of National Defence - Building 16

XLAir responsible for mechanical systems including plumbing, heating, air conditioning

X-L-Air was the Mechanical Contractor responsible for the retrofit of the mechanical system including cutting up and removing two existing chillers, installing two new chillers, re-furbishing two cooling towers, new ducts and VAV systems, new perimeter induction units, new computer room air conditioning, sprinklers and DDC controls.

The work was done while this critical facility remained fully functional around the clock.

General Contractor: Frecon
Project Manager: P.W.G.S.C.
Design By: Clemann Large and Patterson

Experimental Farm Building 55 (Heritage)

XLAir responsible for mechanical systems refit on heritage building

X-L-Air was the prime mechanical contractor responsible for installation of sprinklers, plumbing, DDC controls, heating and air-conditioning.

Work was made more challenging as this is a heritage building. This meant that certain mechanical elements had to be refurbished and re-installed. This included the century-old cast iron perimeter radiation heaters that were taken out, cleaned chemically, sand blasted, painted with baked enamel paint and were re-installed.

General Contractor: Ed Brunet & Associates
Engineer: R.J. McKee Engineering Ltd.
Client: P.W.G.S.C.

Jackson Building Retrofit

XLAir responsible for mechanical systems including plumbing, heating, air conditioning

X-L-Air was the General Contractor. The work included extensive Mechanical retrofit of the main Air Handling Units (AHU's) including installation of new coils, demolition of ducting systems on five floors and replacing with new. New ceilings, lighting, sprinklers and drywalls were installed on these floors. DDC controls were added.

NOTE: All this work was done while the building was fully occupied.

Project Manager: P.W.G.S.C.
Engineer: Zenix
Client: Federal Government of Canada

Export Development Canada - 150 Slater

XLAir responsible for mechanical systems including ventilation

"Design Build Project"

More details about this project can be found on the Design / Build page.

Client: Broccolini Construction
Engineer: Pageau, Morel & Associates Inc.
Prime Mechanical Contractor: X-L Air

Constitution Building

XLAir responsible for mechanical systems including plumbing, heating, air conditioning

Department of Defence & WSIB

Partial retrofit of mechanical and control systems. Project done for the Department of National Defence. X-L-Air was the General Contractor responsible for HVAC, Plumbing, Controls, Sprinklers, T-bar ceilings, dry wall and lighting. The work was done while the building was occupied.

Project Manager: P.W.G.S.C.
Designed by: R.J. McKee Engineering

Jeanne Mance Building at Tunney's Pasture

XLAir responsible for mechanical systems including heating.

X-L-Air was the general contractor. Project included demolition of existing Air Handling Units (AHU's), installation of two new AHU's, installation of a heating system, air distribution system, electrical system and DDC controls for two floors.

Project Manager: P.W.G.S.C.
Design by: R.J. McKee Engineering

12-18 York Street - National Capital Commission

XLAir responsible for installing 2 chillers

X-L-Air demolished the existing chiller plant and installed two new chillers and a cooling tower.

Mechanical Engineer: Clemann, Large and Patterson

Environment Canada ETC Facility Boiler Retrofit River Road, Gloucester

XLAir responsible for mechanical systems including plumbing, heating

X-L-Air was the general contractor. The work involved increasing the capacity of the heating systems by adding one new Buderus boiler, converting another larger Buderus boiler from oil to gas-fired, retrofitting two other boilers, installing new heating systems in part of the building, new pumps, piping, electrical work and DDC controls.

This was a technically challenging project as the ETC complex is Environment Canada's main laboratory, vehicle testing and research facility and had to be kept operational around the clock.

Sir John Carling Building Department of Agriculture, Ottawa

XLAir responsible for mechanical systems including plumbing, heating, air conditioning

X-L-Air was the General Contractor responsible for the mechanical systems retrofit involving new heating coils in the main Air Handling Units (AHU's), new ducting, installation of new gas-fired humidifiers, DDC controls, air and hydronic balancing of all systems and duct cleaning.

Project Manager: P.W.G.S.C.
Design by: Jean Lafontein

National Research Council - Building M-50

XLAir responsible for mechanical systems including plumbing

X-L-Air was responsible for all Mechanical systems to the building M-50 addition (50,000 sq. Ft.) which included new chillers and cooling towers, fan coil units, Direct Digital Controls (DDC controls), sprinklers, plumbing and ducting.

Project Management and Design: NRC

Health Protection Building - Tunney's Pasture

XLAir responsible for mechanical systems refit

X-L-Air was general contractor for the Mechanical Room retrofit. The two main Air Handling Units (AHU's) were completely refurbished including new coils and control dampers. The heating systems were retrofitted and new Direct Digital Controls (DDC Controls) were added. Ceilings and ducting were demolished and replaced with new. The building remained occupied throughout the work period!

General Contractor: X-L-Air Energy Services Ltd.
Engineer: J.R.P. Engineering
Client: P.W.G.S.C.

Forensic Lab Fumehood Hood Certification Ph3

XLAir responsible for mechanical systems including plumbing, heating, air conditioning

X-L-Air was the general/prime mechanical contractor responsible for the ventilation, electrical, and building automation system for this mechanical retrofit, which included replacing the existing AHU fans with two new 75hp fans. This was a fast paced project to be completed over the course of one weekend as the shutdown period was to be minimal.

Project Manager: SNC Lavalin Profac
Engineer: Zenix Engineering
Client: RCMP

Jean Talon - VAV Replacement

XLAir responsible for mechanical systems including plumbing, heating, air conditioning

Location: 3rd to 7th Floor and Basement

X-L-Air was the general/prime mechanical contractor responsible for the ventilation, piping and building automation system.

Project Manager: SNC Lavalin Profac
Engineer: Fox Engineering
Client: P.W.G.S.C.